Cost code

Also called cost category, cost division, CSI code

Definition

A short label from a fixed list (demolition, framing, electrical, permits, labor) tagged on every job cost, so budgets, actuals and estimates line up on every job.

A cost code is the vocabulary job costing speaks. Without one, a receipt from the lumber yard is "lumber" on one job, "framing" on the next and "materials" on the third, and no two jobs can be compared. With a short fixed list, the same receipt lands on the same line every time, the budget for framing can be checked against the actual for framing, and next year's estimate for framing starts from what framing really cost. Commercial firms use the CSI MasterFormat's hundreds of divisions; a small contractor needs about twelve.

A worked number

A remodeler with twelve codes finds, across nine jobs, that "08 Tile and flooring" ran 18% over budget on average while everything else was within 5%. That's not nine bad jobs; it's one bad estimating assumption, fixed once. Without codes, the same overrun is nine unrelated bad months.

The mistake it hides

Too many codes. A list long enough to satisfy an accountant is a list the foreman won't use at the counter, and an unused code is worse than no code, because the receipt gets dumped in "other." The cost codes guide argues for the shortest list that matches how you bid.

In Obra

Categories are the cost codes, kept short on purpose, and every confirmed receipt carries one. The cost code list builder produces a starter list for your trade as a CSV you can import.

Free download

Not ready for an app? Start with our free Excel template.

A ready-made spreadsheet to track costs and income per project — with categories and the totals already set up.

The download starts right away. We'll also follow up by email with more job-costing help — no spam, unsubscribe anytime.